Send Us Plans
ACG · Project Management Reference · Updated May 13, 2026

Commercial storefront installation timeline

Storefront schedule is driven by manufacturing lead time. The 8-14 week factory window is fixed once shop drawings are approved - and it cannot be compressed without an expedite premium. Every week lost in submittal review, design team comments, or late subcontract execution adds directly to the project delivery date. This page documents the typical commercial storefront project schedule phase by phase, identifies the critical path, and explains what GCs and owners can do to protect it. Statewide code path and office map: Florida storefront installation company. Sourced operable-wall specs: Euro-Wall Vista page. System selection and installation scope: commercial storefront systems and installation.

Phase-by-phase timeline

5 BUSINESS DAYS

Bid response

ACG's standard bid response time for a complete set of documents is 5 business days. Incomplete documents (missing structural drawings, no DP schedule, no specifications) extend this. Include the full bid package - architectural, structural, Division 08 spec, and NOA list if specified - with the invitation to bid.

2-3 WEEKS

Submittal preparation

After subcontract execution, ACG prepares shop drawings: plans, elevations, sections, anchor details, glass make-up schedule, hardware schedule, and sealant schedule. HVHZ projects include NOA compilation and DP analysis. Submittal is delivered to the GC for distribution to the design team.

2-4 WEEKS

Design team shop drawing review

Architect and structural engineer review the submittal and return it as approved, approved as noted, or revise and resubmit. Standard industry expectation is 14 days for first review. Complex projects or submittals with comment cycles can extend this to 4 weeks or more. Each resubmittal cycle restarts the review clock.

8-14 WEEKS

Manufacturing

Upon approved shop drawings, frame and glass orders are placed with the manufacturer. Manufacturing lead time is 8-14 weeks depending on manufacturer, system family, finish, and current production queue. This is the critical path item. Standard mill finish ships faster; custom PVDF colors and specialty glass make-ups are at the longer end. Current lead time should be confirmed with the manufacturer at order placement.

1 WEEK

Mobilization and pre-installation

Crew and material mobilization, delivery scheduling, rough opening inspection (per ASTM E2112 and NOA requirements), substrate corrections if needed. Safety setup, temporary protection, and staging area coordination with GC superintendent.

VARIES BY SF

Frame installation

Frame set, anchor, plumb, level per shop drawings. Typical production: 500-800 SF per crew day for standard ground-floor stick-built storefront. Upper floors, occupied buildings, complex configurations, and high-wind-zone work reduce production rates. ACG provides a project-specific installation schedule in the subcontract package.

1-2 WEEKS AFTER FRAME

Glass and glazing

Glass delivery is coordinated for 1-2 weeks after frame installation complete. Glass is inspected at delivery (chips, coating condition, size verification) before installation. Glazing proceeds bay by bay; perimeter sealant is applied after glazing at each section.

1-2 DAYS

Water test

ASTM E1105 water test performed at specified locations (typically 10% of openings or as specified in Division 08). Test results documented and provided to GC. Any failed locations repaired and re-tested. Water testing is performed before interior finishes are complete in the glazing zone.

3-5 DAYS

Punch list and closeout

Punch list items addressed. Closeout package assembled: NOA documentation, approved shop drawings, water test results, hardware warranties, finish certifications, as-built photos. Submitted to GC for project record.

Critical path analysis

The critical path for commercial storefront delivery runs through this sequence:

Subcontract executed → Submittal prepared → Submittal approved → Manufacturing order placed → Manufacturing complete → Installation start

Manufacturing lead time is the single largest non-compressible window in this chain. An 8-week standard lead time means that from approved shop drawings to materials on the jobsite is a minimum of 8 weeks. A 14-week lead time means 14 weeks.

Schedule protection advice for GCs. The most effective schedule protection for storefront is early subcontract award and immediate submittal start. Every week between subcontract execution and submittal delivery is a week added to the back end of the project. A glazing subcontractor who starts shop drawings on Day 1 of execution and delivers a complete submittal in 14 days gives the project a 2-week head start over a subcontractor who starts on Day 14.

Manufacturing lead time factors

The 8-14 week manufacturing window is influenced by several variables that are fixed at the time of order:

FactorEffect on Lead Time
Standard finish (mill, standard colors)Shorter - in standard production runs
Custom PVDF or specialty finishLonger - custom batch required; add 2-4 weeks
Standard glass make-upShorter - glass fabricator has standard runs
Specialty or custom glass (low-iron, bird-safe, fire-rated)Longer - custom order from glass fabricator
Standard system family in current productionShorter
Discontinued or low-volume system familyLonger or unavailable - verify availability early
Manufacturer production queue at order timeVariable - confirm current lead time at subcontract
Order size (economy of scale)Large orders may have negotiated priority scheduling

ACG confirms current manufacturer lead time at subcontract execution and communicates it to the GC in writing. Lead times can change between bid and subcontract, particularly when market demand increases. The contractual lead time is confirmed at order placement, not at bid.

Common submittal delays

Submittal delays are the second most common source of schedule compression on storefront projects, after late subcontract award. The common causes:

  • Incomplete bid documents. Missing structural drawings, no design pressure schedule, incomplete specifications. ACG cannot prepare accurate shop drawings without complete documents.
  • Design development changes after subcontract. Changes to opening dimensions, system family, or glass make-up after shop drawings are underway require revision before submittal.
  • NOA or DP issues. If the specified system does not have a current NOA for the required opening sizes or DP, the submittal cannot be completed until an alternative system is selected and confirmed.
  • Slow design team review. The standard industry review expectation is 14 calendar days. When review takes longer, the manufacturing clock is delayed. GCs should track submittal return dates and escalate when reviews exceed the contractual review period.
  • Revise and resubmit cycles. Each R&R cycle adds another full review period to the schedule. Minimizing R&R requires complete, well-documented submittals.

Trade sequencing

Storefront installation must be properly sequenced with adjacent trades to avoid damage, rework, and water test interference:

  • Before storefront installation: rough opening substrate complete and cured; head flashing rough-in (if required by the design); any embedded anchors set; MEP rough-in in the frame perimeter zone complete.
  • Concurrent with storefront: exterior waterproofing and EIFS at frame perimeter is typically by others but must be coordinated - sealant joint at the frame perimeter requires prior substrate prep by the waterproofing contractor.
  • After frame set, before glass: interior rough framing and blocking adjacent to the storefront can proceed; storefront frame is used as a weather stop during this period.
  • After glazing complete, before water test: perimeter sealant must be fully cured per the sealant manufacturer's specification before water testing - typically 24-72 hours depending on product and conditions.
  • Water test must precede: interior drywall, ceiling, flooring, and any finish work in areas adjacent to the storefront that would be damaged by a water test failure.

HVHZ schedule implications

Miami-Dade and Broward HVHZ projects have additional schedule considerations:

  • Miami-Dade and Broward building department plan review of the NOA-backed submittal is required before a permit is issued. Current review times vary by jurisdiction and workload - plan for 4-8 weeks in the permit process for HVHZ glazing submittals.
  • The permit is a GC-level responsibility, but the glazing submittal is part of the permit package. ACG delivers a complete, accurate submittal package specifically to minimize comment cycles that extend the review period.
  • If the NOA has recently expired or is due to expire during the project, verify current status before beginning design. An expired NOA cannot be used for permit; the alternate system selection and updated submittal preparation adds weeks to the schedule.

FAQ - storefront installation timeline

How long does commercial storefront take from bid to installation?

From subcontract execution to installation start: typically 14-20 weeks. This covers submittal preparation (2-3 weeks), design team review (2-4 weeks), manufacturing (8-14 weeks), and mobilization (1 week). HVHZ projects with permit review add additional weeks.

How long does storefront manufacturing take?

8-14 weeks from approved shop drawings, depending on manufacturer, system, finish, and glass make-up. Standard mill finish ships faster than custom PVDF. Current lead time must be confirmed with the manufacturer at order placement - lead times vary with market conditions.

What can delay a commercial storefront submittal?

Incomplete bid documents, design changes after subcontract, NOA gaps, slow design team review, and revise-and-resubmit cycles. The GC minimizes delay by providing complete documents at bid, tracking review turnaround times, and escalating when reviews exceed contractual timelines.

When should storefront be sequenced relative to other trades?

Storefront frame installation follows rough opening completion. Glass follows frame by 1-2 weeks. Water testing must precede interior finishes in the frame perimeter zone. Storefront perimeter sealant must cure 24-72 hours before water testing begins.

How long does storefront installation take on a typical commercial project?

Approximately 500-800 SF per crew day for standard ground-floor stick-built storefront. Upper-floor, occupied-building, and complex frame work reduces production rates. ACG provides a project-specific installation schedule at subcontract.

What is the critical path item for storefront schedule?

Manufacturing lead time - the 8-14 week factory window that begins only after approved shop drawings. The most effective schedule compression is early subcontract award and immediate submittal start, which protects the full 8-week minimum manufacturing window.

How does HVHZ affect the project schedule for storefront?

HVHZ projects require Miami-Dade or Broward building department plan review, which adds 4-8 weeks to the permit process. ACG provides a complete NOA-backed submittal package to minimize comment cycles. Plan review is on the GC's critical path - early permit submission is essential on HVHZ projects.