Bid & Procurement Hub · ← Back to hub

Commercial glazing submittal process — package contents and timeline

What ACG submits, when it gets submitted, and what GCs and architects need to do to keep the review cycle from stalling the fabrication clock. Division 08 submittals are more complex than most trades and require PE engineering in Florida.

By Connor Walsh · President, American Commercial Glass · FL CGC #1531993 · FAA Commercial Pilot · Published May 2026

The short answer

A Division 08 submittal package includes shop drawings, product data, a glazing schedule, PE-stamped engineering, and NOA cover sheets for HVHZ work. First review takes 10–21 days. Material is not released to fabrication until ACG has an "Approved" or "Approved as Noted" response. Total cycle time: 4–8 weeks in most markets.

FL CGC
#1531993
350+
Projects completed
1M+ SF
Glass installed
$3M / $6M
Bond capacity
Zero
OSHA recordables since 2021
3 offices
West Palm · Naples · Tampa

Why the submittal process matters for glazing lead times

Curtainwall has a fabrication lead time of 10–18 weeks from release-to-fab. Storefront runs 6–10 weeks. ACG cannot release material to fabrication until the shop drawings are approved. If the submittal review cycle runs long — because the package was incomplete, or because a re-submittal cycle was required — the entire schedule slips. The submittal process is not a paper exercise; it is the gating event for the entire glazing scope.

ACG's practice is to submit a complete, first-rate package on the first cycle. A well-prepared submittal clears review in one cycle. A sloppy or incomplete submittal cycles back, costs 2–3 weeks, and forces the schedule.

Submittal package contents — full list

DocumentWhat it coversRequired for
Shop drawingsFrame plan, elevations, details, anchor conditions, glass biteAll systems
Glazing scheduleAll openings: mark, size, frame type, glass makeup, hardwareAll systems
Product data sheetsManufacturer's published product data for framing, glass, hardware, sealantsAll systems
Florida Product Approval (FPA)State-level product approval listing for each assemblyFBC projects (non-HVHZ)
Miami-Dade NOA cover sheetsNOA packet for each frame + glass + anchor assemblyHVHZ projects
PE anchor calculationsSigned-sealed structural engineering for all anchor conditionsCurtainwall; required by FBC
PE frame engineering reportSigned-sealed framing analysis for spans exceeding span chart limitsNon-standard spans
Mockup spec / test planLocation, size, construction method, and test standard for mock-up assemblyWhen spec or AHJ requires
AAMA 502 test planField water test procedure and scheduleWhen required by spec
Sample schedulePhysical samples of frame finish, glass, sealant colorWhen spec calls for samples
Warranty documentationManufacturer's warranty terms and periodsUsually at closeout; sometimes at submittal

Submittal timeline — typical schedule

Week 1–2: Pre-submission preparation

ACG receives approved RFI responses and confirmed project information (slab-to-slab dimensions, anchor conditions, finalized glass spec). We begin shop drawing production and coordinate with the manufacturer's detailer for custom conditions. Glazing schedule is drafted parallel to shop drawings.

Week 3–4: PE engineering and NOA assembly

Anchor calculations are sent to the PE for stamping. On HVHZ projects, the NOA packets are pulled and confirmed against the final frame/glass/anchor combination. Product data sheets are compiled. Sample submittal is assembled and transmitted to GC.

Week 4–6: Architect review (first cycle)

Typical architect review is 10–14 calendar days for standard glazing, 14–21 days for curtainwall. If the submittal includes PE engineering for the EOR's review, add 5–10 days. Procore tracks the review clock and ACG escalates if the return date passes.

Week 6–8: Second cycle if required (resubmit)

If the architect returns comments requiring revision, ACG addresses every comment with a response matrix, revises drawings, and resubmits. A clean second submittal typically clears in 7–14 days. ACG tracks the revision clouds to show exactly what changed between cycles.

Week 8+: Approved drawings — release to fabrication

With approved drawings in hand, ACG releases the order to the manufacturer. Fabrication lead times begin from this date. On a 14-week curtainwall, that puts delivery 14 weeks out from approval — building the case for a well-run submittal process as early as possible.

FBC vs HVHZ — submittal differences

FBC (non-HVHZ) submittal requirements

Outside Miami-Dade and Broward (the HVHZ), Florida commercial glazing requires Florida Product Approval (FPA). FPA documentation shows the state approval listing number, the approved assembly configuration, and the applicable test standards. Shop drawings reference the FPA number and confirm the installed assembly matches the approved configuration. PE anchor calcs are still required for curtainwall.

HVHZ submittal requirements

Inside the HVHZ, every assembly must hold a Miami-Dade Notice of Acceptance. The submittal includes the full NOA packet for each assembly, with NOA number, approved configuration, and product approval parameters. The shop drawings must show that the installed assembly matches the NOA-listed configuration. HVHZ permits may also require a third-party special inspector to verify compliance during installation. ACG works with approved HVHZ inspectors on every Miami-Dade and Broward project.

Submittal coordination points with other trades

Glazing submittals intersect with three other trade submittals: structural steel (embed plates and anchor conditions), caulking / waterproofing (sealant type and joint design), and door hardware (hollow metal frame prep and hardware blocking). ACG coordinates submittals with these trades before submitting to avoid re-submission cycles caused by conflicts discovered during the architect's review.

Frequently asked questions

What does a commercial glazing submittal package include?

Shop drawings, product data, glazing schedule, PE-stamped anchor calculations, Florida Product Approval or Miami-Dade NOA cover sheets, and mockup specs where required. See the table above for the full list by project type.

How long does the review cycle take?

First review: 10–21 calendar days. With PE engineering review: add 5–10 days. A resubmit cycle adds 7–14 days. Total from ACG submittal to approved drawings: 4–8 weeks in most markets.

Does ACG provide PE-stamped engineering?

Yes. Anchor calculations are signed and sealed by a licensed Florida PE on every curtainwall scope. Frame engineering reports are provided for non-standard spans or conditions outside the manufacturer's published span charts.

What is the difference between FBC and HVHZ submittal requirements?

FBC (non-HVHZ) projects require Florida Product Approval documentation. HVHZ projects require Miami-Dade Notice of Acceptance packets for every assembly, which are more extensive and may require special inspection during installation.

What happens if submittals are rejected?

ACG responds to every comment with a response matrix, revises drawings with revision clouds, and resubmits. Material is not released to fabrication until we have a final approval.

When is a mockup required?

Mockups are required when the specification calls for one, when AAMA 502 field water testing is required, or when the AHJ requires proof of performance. HVHZ projects may require TAS 202 field testing as a permit condition. ACG builds and tests mockups as part of scope on applicable projects.

Send drawings to ACG

Share your drawings and specs. ACG will review the submittal requirements and give you an accurate timeline from submittal to approved drawings and fabrication release. FL CGC #1531993. 350+ projects. $3M/$6M bonding.

Submit plans →  |  RFI process →  |  Back to hub →

Related resources

Full Commercial Glass Scope

Not just impact glass. Every commercial glass system.

ACG installs the full CSI Division 08 (Openings) scope across the state — hurricane-zone and inland. Whether the project needs ESWindows impact-rated curtain wall in Miami-Dade or standard architectural storefront in Orlando, the same team delivers.

ACG is expanding

Florida-built. Tennessee next. Nashville office opening Q3 2026.

After delivering 350+ commercial glazing projects across Florida, ACG opens its Nashville office in the third quarter of 2026. The same AI-augmented operating model, the same Division 08 single-source scope, brought to the Tennessee commercial construction market — office, multifamily, retail, hospitality, healthcare.

Nashville early-bid list