Florida Glazing Permit Timeline by County

Average commercial glazing permit review times for Florida's 13 most-active commercial counties. Based on ACG's project submittal records 2022-2026.

County Zone Permit NOA Review Notes
Miami-DadeHVHZ15-25 days30-60 daysStrict NOA enforcement. Plan extra time for first-submittal rejections.
BrowardHVHZ12-22 daysStandard NOA reviewGenerally faster than Miami-Dade. NOA acceptance straightforward.
Palm BeachWBDR10-18 daysStandardNot HVHZ. Florida Product Approval is the path.
CollierWBDR10-15 daysStandardNaples has separate municipal review on top. Plan 1-2 extra weeks for City of Naples.
LeeWBDR10-18 daysStandardFort Myers and Cape Coral have separate municipal reviews. Post-Ian backlog can stretch this.
MonroeWBDR severe12-20 daysStandardFlorida Keys severity drives 180 mph design wind. Plan extra time for specialty assemblies.
HillsboroughWBDR coastal10-15 daysStandardCity of Tampa has separate review. Inland Hillsborough is faster.
PinellasWBDR10-15 daysStandardSt Pete and Clearwater have separate municipal reviews.
OrangeStandard FBC7-12 daysStandardInland - no NOA required. Faster permit cycle than coastal counties.
SarasotaWBDR10-15 daysStandardCity of Sarasota separate review. Generally efficient AHJ.
DuvalWBDR coastal10-15 daysStandardConsolidated city-county (Jacksonville). Single AHJ - simpler than multi-AHJ South Florida.
LeonStandard FBC7-12 daysStandardTallahassee. Inland. Fast permit cycle.
BrevardWBDR10-15 daysStandardSpace Coast. Multiple municipal AHJs (Cocoa, Melbourne, Palm Bay).

Times are typical commercial glazing review windows. Complex assemblies, first-time NOAs, structural deviations, and overloaded review queues can extend these. Always confirm with the specific AHJ before relying on a number for your schedule.

How to compress your permit timeline

  • Submit a complete package the first time. Missing NOA references, design pressure mismatches, and anchorage detail issues are the top three rejection causes.
  • Use stock NOA assemblies. Custom assemblies that require new NOA review add 30-60 days.
  • Choose qualified glaziers with documented submittal experience in your AHJ. ACG submits in all 25 Florida commercial counties.
  • Coordinate structural opening dimensions with the GC BEFORE shop drawings. Re-engineering after framing changes adds 2-3 weeks.
  • Time the submittal to the AHJ's review queue. Mondays after holidays are the worst; Tuesday-Thursday of mid-month is the best.