GC Resource / Prequalification Reference

Glazing Subcontractor Prequalification — Sample Packet

What this is. A working template Florida GCs can use to prequalify glazing subcontractors before bid invitation. Sections mirror AIA A305 with HVHZ-specific additions. ACG meets every line item.

Section 1 — Identity and Licensing

FieldWhat to verify
Legal entity nameMatch Florida Division of Corporations record (sunbiz.org)
FEINW-9 on file, dated within 12 months
Florida licenseCGC or CGI active, verified on myfloridalicense.com
Years under current licenseLapses or transfers flagged
Qualifying agentNamed individual, license tied to the entity
DBPR disciplinary historyPast 5 years — any settled complaints or formal action

Section 2 — Bonding

FieldWhat to verify
Surety nameTreasury Listing (Department of Treasury Circular 570) confirmed
A.M. Best ratingA- or better preferred
Single-project limitMinimum 3× project value
Aggregate limitMinimum 6× project value
Date of letterWithin 90 days
Producer / agencyNamed, with direct contact for verification

Section 3 — Insurance

CoverageRequired minimumVerify
General Liability$1M / $2MPer occurrence / aggregate; products-completed ops included
Excess / Umbrella$5M (or $10M on $5M+ projects)Follow-form over GL, auto, employers liability
Workers CompensationStatutory FLFlorida coverage; no contracting state exclusions
Auto$1M CSLHired and non-owned included
Additional InsuredPrimary, non-contributoryGC, owner, lender named on ongoing and completed ops
Waiver of subrogationIn favor of GC, owner, lenderOn GL, auto, WC
Notice of cancellation30 days writtenEndorsement on COI

Section 4 — Financial Capacity

Section 5 — Safety

Section 6 — Product and Code Compliance (HVHZ-specific)

Section 7 — Manufacturer Certifications

For ACG, the verified manufacturer certifications carried are:

For any bidder, ask for the certificate (current year) and verify directly with the manufacturer. Cert numbers and expiration dates are useful for the prequal file.

Section 8 — Experience and References

Section 9 — Field and Office Capacity

Frequently Asked Questions

What is glazing subcontractor prequalification?

The vetting process a GC or owner runs before inviting a glazing sub to bid. Covers license, bonding, insurance, financials, safety, references, and manufacturer credentials.

What documents are required?

License, bond letter, COI, two most recent year-end financials, OSHA 300 logs, EMR letter, project list, three references, manufacturer certifications, safety plan, and quality plan.

How often should glazing subcontractors re-prequalify?

Annual recertification. Bond letters and COIs typically every six months or before each award.

What is AIA A305?

AIA's Contractor's Qualification Statement — a standardized prequalification form covering license, bonding, financials, references, completed projects, and litigation history.

How does ACG meet these standards?

FL CGC #1531993, $3M / $6M bonding, $5M umbrella, zero OSHA recordables across 350+ projects, seven manufacturer certifications, three Florida offices, named PM + superintendent per project.

Need ACG's current prequalification packet for your GC bid list? Request it directly and a complete packet will be returned within 24 hours.

Request the ACG Prequalification Packet