Restaurant Glass Walls and HVAC Coordination Connor Walsh · 2026-09-12 · /blog/restaurant-glass-walls-hvac-coordination.html

Live folding-wall pages mention HVAC coordination in a short line. This article expands that into an MEP interface worksheet for open-wall and closed-wall restaurant operation.

Two operating modes, one dining room

Closed-wall mode is a conditioned envelope with operable joints sealed. Open-wall mode is closer to a covered patio with indoor equipment still running nearby. Humidity, grease exhaust, and guest comfort change between those modes. Design the controls conversation around both, not only peak summer closed-wall load.

What the MEP designer needs

  • Which openings operate, how often, and for how long during service
  • Whether staff can leave walls partially open
  • Zoning map: dining, bar, kitchen, vestibule
  • Door / wall status intent if any sensors are proposed (optional; not mandated here)
  • Kitchen exhaust and makeup-air assumptions when the dining wall is open

Glazing contractors can describe how the wall opens. They do not design the HVAC system. Keep roles clear.

Interface points (process)

  1. Architect marks operable opening marks and stacking on plans.
  2. Owner states expected open-wall hours and seasons.
  3. MEP proposes zoning and control strategy for open vs closed.
  4. GC coordinates rough-in if any wall-position sensors or operators need power/low-voltage.
  5. Glazing sub provides shop drawings showing panel motion so sensor placement (if used) does not conflict with tracks.

Open / closed wall worksheet

TEMPLATE ONLY. MEP interface worksheet. Not a universal interlock design.

Topic Closed-wall Open-wall
Owner hours / season note _______ _______
Zones affected _______ _______
Kitchen exhaust interaction MEP note MEP note
Partial-open allowed? N/A Y / N / staff rule
Any wall-status sensor? Y / N Y / N
Power / LV rough-in owner _______ _______
Commissioning note _______ _______

What not to prescribe here

  • No universal requirement that walls must interlock with HVAC
  • No setpoints, CFM values, or equipment schedules
  • No claim that opening the wall always saves energy or always wastes energy

How to ask for the right scope

Send elevations, the opening schedule, and a one-page owner note on expected open-wall hours. Ask MEP and glazing to meet once before shops. Mark material-only or furnish-and-install for the glazing package.

ACG works from West Palm Beach, Naples, and Tampa. Call (772) 486-7711. FL CGC #1531993.

Frequently Asked Questions

Do operable glass walls require HVAC interlocks?

Not universally. Some projects use wall-status inputs; many rely on staff procedures and zoning design. The MEP engineer decides. This article does not prescribe interlocks.

Who designs the open-wall HVAC mode?

The MEP designer, using owner operating assumptions and architect opening marks. The glazing sub coordinates motion and any rough-in that touches the wall.

Can ACG provide CFM or setpoints?

No. Those belong in the engineered HVAC documents.

What should I send?

Elevations, opening schedule, open-wall operating notes, and material-only vs furnish-and-install.

Related Resources
Folding Walls FL → Folding vs Multi-Slide → Flush Thresholds → Restaurant Glazing →
SEND THE DRAWINGS

Open-wall dining?
Bring MEP to the table early.

Send elevations, the opening schedule, and a one-page open-wall hours note. Mark material-only vs furnish-and-install. (772) 486-7711. FL CGC #1531993.

Send Us Plans
Pricing this scope?

Send us the drawings. Scope letter back in 48 hours.

American Commercial Glass coordinates operable restaurant glass walls with Florida GC and MEP teams. Send elevations, the opening schedule, and operating assumptions.

Licensed Florida glazing subcontractor · FL CGC #1531993 · West Palm Beach · Naples · Tampa

Send us plans → (772) 486-7711