Global phase durations live on the commercial glazing project timeline. This page is building-level partial turnover control.
Why partial turnover needs its own tracker
Campus and multi-building schedules often occupy Building A while Building C is still in fabrication. If punch and closeout wait for the last building, early buildings enter service without complete records, and warranty start logic gets fuzzy.
Building-level tracker (template)
TEMPLATE ONLY. Multi-building glazing turnover tracker. Not a project record. Not a statutory inspection checklist.
| Building ID | Glass complete | Inspection / punch closed | As-builts filed | Warranties indexed | Owner acceptance dated |
|---|---|---|---|---|---|
| Bldg A | Yes / No / date | Open items count | Yes / No | Yes / No | Yes / No |
| Bldg B | |||||
| Bldg C |
Inspection and punch sequence
- Define what "building complete" means for glazing (all openings, or a named phase).
- Hold a building-level inspection with the GC and design team as required by the contract.
- Close punch items that affect weatherproofing before owner occupancy of that building.
- Carry cosmetic items on a dated list with responsibility and access notes.
- Do not mix Building A punch into Building C's list without clear labels.
Records that must not wait
- Approved shop drawings for that building's configurations
- Product-approval documents for installed systems
- Condition photos and punch clearance
- Warranty documents indexed to the building
- Facilities asset-register rows for that building
How to ask for phased turnover
State the building release sequence at bid time. Send the campus schedule and opening counts by building. ACG: (772) 486-7711. FL CGC #1531993.
Frequently Asked Questions
How should multi-building glazing jobs handle partial turnover?
Track inspection, punch, as-builts, and warranties per building. Do not wait for campus-wide completion to file early-building records.
Is this the same as a global project timeline?
No. The timeline article covers phases. This page covers building-level acceptance and document control.
When do warranties start on a partial turnover?
Follow the contract and manufacturer terms. Do not assume a single campus-wide start date without written confirmation.
What should a GC send for phased glazing turnover planning?
Building release sequence, opening counts by building, and whether early buildings will be occupied before later buildings complete.